Boom Deployment Sequence
Follow the standard 7-step procedure for safely deploying a knuckle boom crane from stowed to operational position. Based on the yellow sticker deployment diagram.
Step 0 of 7
Loading Palfinger crane model...
LMB Orbit RMB Pan Scroll Zoom
AS 2550 — Cranes
All crane deployment must follow manufacturer procedures and AS 2550 safe use requirements. Never operate under power lines. Ensure ground conditions can support loads.
All crane deployment must follow manufacturer procedures and AS 2550 safe use requirements. Never operate under power lines. Ensure ground conditions can support loads.
Loading Model...
Please wait while the 3D crane model loads.
Deployment Complete
The knuckle boom is now fully deployed and ready for operation. All 7 steps of the deployment procedure have been completed correctly.
Remember: Before lifting any load, verify Rated Capacity charts, check wind conditions, and confirm ground conditions per AS 2550.